Case Study

W.P:R. Service Srl Saves Positano's Pipeline with Rapid ASOE Pipeline Rehabilitation

Emergency Rehabilitation of a Critical Supply Pipeline Serving Positano, Italy

Client Challenge

W.P:R. Service Srl was contacted in a critical situation where traditional pipeline repair methods were impossible. A vital supply pipeline serving the popular tourist destination of Positano was failing. The situation was compounded by:

  • High Tourist Traffic: Positano was experiencing peak tourist season, requiring uninterrupted water supply.
  • Scheduled Event: A major bicycle tour of Italy was scheduled to pass through the area imminently.
  • Complex Infrastructure: The pipeline was embedded in reinforced concrete, making traditional excavation extremely difficult and costly.
  • Regulatory Restrictions: ANAS, the Italian national roads authority, prohibited excavation in the area.
  • Imminent Failure: The pipeline was on the verge of failure, threatening critical water supply.

The client faced a potential crisis with no apparent alternatives, leading to significant panic.

W.P:R. Service Srl Solution

W.P:R. Service Srl deployed their expertise in ASOE Pipeline rehabilitation, utilizing advanced pipe-in-liner technology. The team implemented a rapid, trenchless repair solution, overcoming the logistical and regulatory challenges.

Key Benefits & Outcomes:

  • Rapid Deployment: The entire rehabilitation process was completed in less than 7 hours, preventing any disruption to the water supply.
  • Trenchless Installation: The ASOE Pipe in Liner system was installed without any excavation, avoiding disruption to the concrete footpath, tourist traffic, and the scheduled bicycle tour.
  • Regulatory Compliance: The trenchless solution adhered to ANAS regulations, avoiding any potential conflicts.
  • Minimal Disruption: Tourists and residents experienced no interruption to their water supply.
  • Client Satisfaction: The client expressed profound gratitude, stating, “You saved us,” highlighting the success of the project.

Client Value

W.P:R. Service Srl’s expertise in ASOE Pipeline rehabilitation provided a crucial solution in a time-sensitive and challenging situation. The ability to rapidly deploy a trenchless solution prevented a major crisis, saved the client from significant logistical and financial burdens, and ensured the continued flow of water to a vital tourist destination.

Technology Used

  • ASOE’s advanced pipe-in-liner system

Conclusion

This case study highlights Mullane Trenchless’s commitment to delivering innovative and sustainable solutions for pipeline rehabilitation. By leveraging advanced trenchless technology, Mullane Trenchless helps clients minimize disruption, reduce costs, and extend the lifespan of their critical infrastructure.